Mehlville receives 16 bids for new district auditorium


Auditorium construction work possibly could begin Nov. 1


Kari Williams
Staff Reporter
October 10, 2012 - Mehlville School District officials narrowed down 16 bids for its auditorium project — all of which were less than the $6 million budget — to four and will have a recommendation to present to the Board of Education when it meets Oct. 17.

Director of Facilities Steve Habeck told the Facilities Committee last week district officials will conduct interviews with the "bottom four" companies this week. The base bids for the four low bidders are: Orf Construction, $5,175,000; Trico Construction, $5,175,000; Lamb Construction Co., $5,165,800; and Wright Construction Services, $5,134,000.

Bids for the four companies with four proposed alternates — connecting corridor, loudspeakers, audio mixing console, wireless microphone, backstage TV and distribution and gypsum board in the auditorium — are:

• Orf, $5,425,400.

• Trico, $5,414,520.

• Lamb, $5,414,800.

• Wright, $5,342,700.

Regarding alternates, Facilities Committee member Tim Hudwalker said the connecting corridor is "probably a big decision."

"I would say a lot of the rest of those could be deferred," he said. "I would say you want to do the (gypsum) board in the auditorium now because you can't go back and do that."

Board member Ron Fedorchak, who attended the meeting, said he agreed with Hudwalker's opinion on the corridor.

"I want to do this right," he said. "I want this building to look good for 50 years, 100 years."

Superintendent Eric Knost told the Call though there are change orders with all construction projects, he would like there to be as few change orders as possible once the contractor is selected.

"I'm just adamant of keeping this job in budget ...," Knost said. "Even with all alternates, we feel that we can run with those alternates and keep it in budget. But I don't want any surprises."

The superintendent said he does not want to select a general contractor then discover after the fact the contractor believes there was an error or omission in the construction documents the district would have to pay for because of a change order.

"I can tell that people are looking at me like I have three heads with some of the things I'm saying, but I'm just that intent we don't need a construction project that goes awry," Knost said, "and that's why I've been so adamant about all the due diligence in this project."

The potential start date for auditorium construction is Nov. 1.


Tags: Mehlville School District News


  • Related Editorial
    Sports
    Football Tigers defeat Fox 21-14
    Oakville's first win of season a confidence-builder
    Sep 17 2014
    The Oakville Senior High School varsity football team got a much-needed victory Friday night, defeating Fox 21-14....
    Sports
    Panthers roll over Seckman 33-9
    First win of season gives Mehlville some momentum
    Sep 17 2014
    The Mehlville Senior High School varsity football team started the 2013 season exactly the same way as the 2014 season is unfolding....
    School News
    Field hockey program a real success story
    Willie tapped as head coach of Oakville field hockey team
    Sep 17 2014
    After being cut from the soccer team 13 years ago, Oakville High School freshman Carrie Lampe decided if she couldn’t play that sport, she would find one of her own — field hockey....
    School News
    VIDEO: Meet the football Tigers’ ‘secret weapon’
    Freshman wears many hats for Oakville team
    Sep 17 2014
    Freshman Drew Yost is a member of the Oakville High School football team, but you won’t find him on any roster and he has a grand total of zero touchdowns or quarterback sacks so far this season....
    Impact News
    Local meeting guide 2014
    Jan 08 2014
Site Search


Weather
Type in your zip code and click "Go" to get your 7-day forecast.
Visit www.crh.noaa.gov