Eardley casts lone 'no' vote on contract for new district tennis courts


With three rebates, project right at budget of $450,000


Kari Williams
Staff Reporter
October 03, 2012 - Mehlville Board of Education member Kathleen Eardley cast the only vote last week against approving a $513,896 contract to construct tennis courts at Bernard Middle School.

Eardley told the Call she believes spending "half a million" dollars on the tennis court project is "a little excessive."

"And it's fuzzy math, too, when you look at where it is to get under the $450,000 budget," she said. "We're taking a rebate and applying it to something that has nothing to do with the rebate to get (to) that under-budget mark."

The board unanimously approved Superintendent Eric Knost's facilities plan in December, which included $450,000 to construct eight tennis courts at the middle school.

The district received five bids ranging in price from $524,806 to $826,000 for the tennis courts. Knost recommended the low bid from Byrne & Jones Construction for approval.

Byrne & Jones' base bid totaled $524,806.

With three rebates — U.S. Tennis Association, $37,500; USTA Missouri Valley, $20,000; and American Express, $21,730 — the cost comes in at $445,576.

The American Express rebate is from a card the district uses "specifically to pay bills, not run a balance on," according to Knost. Knost said the district has known for "quite a while" the money from American Express would be coming in at the amount presented.

Because district officials want to "make an effort to keep (the cost) within that $450,(000)," it was attached to the project.

Value engineering also is expected to reduce the cost by $10,910, bringing the bid down to $513,896 — the amount approved by the board. Knost said value engineering is asking the contractor to consider options that would "drive the price further down" and are not affected by USTA specifications, St. Louis County or Metropolitan St. Louis Sewer District guidelines and permitting.

A value engineering example Knost gave at the board meeting was to "seed and straw" instead of sodding the Bernard site.

A contingency of roughly $15,000 puts the total cost right at the $450,000 budget.

Information provided to the board also includes two alternates for lighting. The board did not approve the alternates. Knost said he never brought the project to the board suggesting lights, but it was requested during the process.

Director of Facilities Steve Habeck said it does not benefit the district to have any work completed now for future installation of lighting at the courts. There are "really no savings" to preparing for lighting now, Habeck told the board.

Habeck said Byrne & Jones is "basically the biggest sports complex installer" in the Midwest. The company has installed tennis courts at multiple St. Louis schools, including Ladue and Lindbergh high schools.


Tags: Mehlville School District News


  • Related Editorial
    Opinions
    Felton’s MSBA presidency will benefit school district
    'Call the Tune' by Mike Anthony
    Jun 29 2016
    The Mehlville Board of Education’s longest-serving member, Larry Felton, recently took office as the new president of the Missouri School Boards’ Association, or MSBA....
    Impact News
    Mehlville board OKs budget; Palamand, Murphy opposed
    Two want separate vote on pay hike for classified staff
    Jun 29 2016
    A $115 million budget approved by the Mehlville Board of Education last week restores many of the cuts made last year and includes the new spending the district promised voters under Proposition R....
    Impact News
    Proposed apartments meet fierce opposition
    Citizens question accuracy of traffic study for proposal
    Jun 29 2016
    The neighbors who would surround a large apartment complex proposed along Tesson Ferry Road say the development would permanently change the character of their quiet neighborhoods, drag down property ...
    School News
    Blades Elementary garden earns award
    Jun 29 2016
    The Blades Elementary Community Garden topped hundreds of gardens last week to win ‘Best Garden to Be a Kid In’ in Gateway Greening’s Garden Contest. More than 60 volunteers built Blades’ new garden, ...
    Opinions
    Felton’s comments on merit pay make former board member laugh
    Letter to the Editor
    Jun 22 2016
    To the editor: I had to laugh when I read Mehlville Board of Education member Larry Felton’s comments in the June 2 issue of the Call newspaper about merit pay for Mehlville School District employees....
St. Louis Spa
Huelsman's Jewelers
Site Search


Weather
Type in your zip code and click "Go" to get your 7-day forecast.
Visit www.crh.noaa.gov